12,019,568
kWh pe
830,845
€
2,941
t
Lighting
Light equipment has been refurbished in selected hospital areas implementing energy saving strategies based on presence detection, luminance level optimization and time schedule based control. Bus connected LED lights and presence sensors guarantee improved efficiency and high light source lifetime together with extended control capabilities.
Data Center Cooling
Energy consumption needed for data center cooling is reduced operating on system management and avoiding new hardware installation. The cooling system is optimized predicting external air temperature, regulating drycoolers and pumps speed and extending the use of indirect freecooling with a wider range of external temperatures.
79 %
824,354
kWh pe
123,653
€